Parking Committee Accomplishments

Mission/Goals | Agenda | Members | Accomplishments | Projects

2007-2008 Accomplishments

Parking Garage Needs Assessment Study: 

The Parking Garage Needs Assessment Study concluded in late 2007.  The details of this important study may be found below: 

BACKGROUND 

Over the last two years the City has been involved in a parking garage study.  In January 2006, we issued an RFP for a Downtown Parking Garage Needs Assessment Study.  The intent was to hire an engineering consulting firm to conduct a downtown two-stage parking garage analysis that would provide a multi-story parking garage needs assessment, and based on the findings of the needs assessment, either provide preliminary multi-story garage site selection, conceptual design, cost estimates and economic feasibility of a multi-story garage – or – provide recommendations on improving the parking availability and efficiency in downtown Newark that do not include a multi-story garage construction.  

Once proposals were received, a Parking Garage Needs Assessment Steering Committee was appointed to assist in the consultant selection process.  Specifically, the committee was tasked with reviewing the proposals submitted for the RFP, meeting with selected firms, and developing a recommendation on which firm to hire to conduct the study.  The committee was also appointed to provide oversight and ensure an unbiased study, review the final product and provide a recommendation on how to proceed from that point forward.  Steering Committee Members included John Newcomer, DNP Parking Committee Chairman; James Grimes, Assistant Director of UD Public Safety; Joseph Wald, Newark resident and former Chairman of the Planning Commission; Richard Handloff, downtown business and property owner; Carol Houck, Assistant to the City Manager; Andrew Haines, Parking Administrator; and Maureen Feeney Roser, Assistant Planning and Development Director and DNP Administrator.  The steering committee met, reviewed and ranked the 9 RFPs submitted for the project, interviewed the two top ranked firms, and unanimously recommended that Desman Associates be hired to conduct the Parking Garage Needs Assessment Study.  City Council awarded the contract to Desman Associates in March 2006. 

PROCESS

The Steering Committee met with Desman Associates on April 11, 2006 to review the scope of work and timeframes for the study, provide data Desman Associates requested to successfully complete the study, define the study boundaries, and make suggestions for stakeholders to be interviewed as part of the process.  

The study area approved by the Committee is the area bounded by Tyre Avenue to the East, Delaware Avenue to the South, Elkton Road to the West and the CSX Railroad tracks to the North.  The study was divided into Phases - the first being an analysis of parking supply and demand and determination of future parking demand; and the second a parking structure conceptual design and financial feasibility analysis or alternate recommendations to improve parking. 

 

PHASE ONE

Phase One involved an inventory of spaces, an occupancy survey, a determination of practical capacity and stakeholder interviews.  Therefore, an inventory of all parking (on street and off street) in the study area was conducted.  The area contains a total of 1,849 parking spaces.  198 or 11% of the total are on-street meters and 1,651 (89%) are off-street parking spaces.  Of the 1,651 off street spaces, 655 of them or 33% are located in municipal pay-to-park hourly lots (Lots 1, 3, 4), 117 or 7% are in monthly permit lots (Lots 2, 5), and 966 or 60% are in private customer only parking lots.  To determine the utilization of these spaces, Desman conducted parking occupancy surveys on Thursday April 27, 2006 from 8 AM to 6 PM and Friday, April 28, 2006 from 10 AM to 10 PM.  The data collection periods were selected and approved by the committee to provide data from different demand times so that the study group could establish a peak, weekday utilization period for the downtown area.  

The process revealed two peak periods for on and off street parking downtown – 12 PM and 8 PM.  This peak occupancy information was further refined in terms of “practical capacity.”  Desman notes that the term practical capacity relates to “the overall efficiency of a parking facility and is also used as another measure of stress on the system’s supply.  A parking facility is perceived by its users to be full when occupancy levels reach 85-95%.  Once this level is exceeded, potential parkers find it difficult to find an available space.  The effective and efficient turnover of convenient parking spaces is most successful when the supply of spaces exceeds the parking demand for those spaces by 5-15%.”  For the study, therefore, Desman used a 90% practical capacity for all parking facilities in study area.  Using this measure, on-street parking totals revealed an 80% occupancy rate during peak periods, while off-street showed 72% occupancy total at peak.  It is important to note, however, that the average for total off-street space occupancy rates showed marked differences between private customer lots and public pay to park lots.  In fact, Lots 1, 2 and 4 had occupancy rates of 98, 100, and 96% occupancy levels respectively.  This finding, along with a review of private lot locations within the study area led to a further refinement of the study area by geography.  The study area was, therefore, divided into two geographic areas to better understand the current parking supply and demand conditions, especially as they apply to the “core businesses” in downtown.  Chapel Street was used to separate downtown Newark into east and west districts for study purposes. 

The East District which includes parking generators such as the Newark Shopping Center and Market East Plaza was determined to be clearly under-utilized, with peak occupancy for the parking facilities at only 55% at 12 PM – and metered parking averaged only a 30% occupancy rate at the same time period.  The result is a practical surplus of 288 spaces at peak occupancy in the East District. On the other hand, the West District had 83% occupancy during the peak period, and a number of facilities in the district experienced practical parking deficits.  Lots 1, 2 and 4, as well as the Christina School District lot, had combined peak occupancy at 12 PM of 96% - well beyond recommended levels. 

In addition to the analyses above, interviews with various stakeholders and city staff were also conducted in Phase One in an effort to determine if there is any consensus in regards to the perspective of public parking in downtown Newark.  The interviews also helped determine if perceptions about parking are in line with the empirical realities.  Through the interviews, the consultants found that, while not all believe that there is an actual shortage of parking spaces available, most believe that Newark is perceived as having a lack of parking, and as a result, faces a deterrent to economic development.  

Finally, regarding future conditions which may affect parking supply and demand, the consultants reviewed potential development projects as well as vacancies in the study area.  Unfortunately, most of these potential parking demand generators are located in the western district of the study, placing more stress on the limited supply in that area.  Taking all this information into account, the consultants concluded that, despite the current public perception, there is currently adequate parking in downtown Newark.  The West District of the downtown area, where many of the restaurants are located, has significantly less available parking at peak occupancy than the East District, and with the potential developments in the area, the consultants believe that, while current levels do not constitute a deficiency, in the short term, a deficit will exist in the west district.  Therefore, they recommend four options to address the potential parking deficit:

1.  Better utilize the available parking in the east section of downtown combined with a Main Street shuttle – the potential advantage of this is, other than the shuttle, there would be no parking investment required by the city.  Having said that, the consultant conceded that customers using establishments downtown would not find this option acceptable either from a level or service or convenience perspective.

1.  Expand current surface parking – this option was offered as the most cost effective way to provide additional municipal parking.  The trouble with this recommendation is that the city leases much of its current municipal parking and has not accumulated a lot of land over the years to expand surface parking.  In addition, its appears that there is limited land available around existing surface parking areas to expand surface parking.

2.  Build Structured Parking – The advantage of this option is that it is a more effective use of land.  The disadvantage is, of course, the cost to build it.  Having said that, the consultants found that building at least a net 250 space parking garage would help the city overcome the perception of inadequate parking; provide adequate parking for the new developments anticipated over the next few years, provide enough parking to stimulate economic development of “undeveloped parcels” downtown; and send a message to the business community that the city is a willing partner and wants businesses to succeed in Newark.

3.  Issue a moratorium on any future parking space ordinance waiver and require businesses to build to Code.  This option requires no direct financial investment in parking by the city, but could prevent private developments from being built.

In the Phase One report conclusion, Desman Associates indicates that the City of Newark is at a crucial point in how we approach parking downtown and makes a series of recommendations to improve downtown parking, several of which we are already working on, at least in part.  For example, one recommendation was to consolidate all the elements of parking to include on street and off-street, including enforcement, within the Parking Division which is proposed in part for the 2008 budget (the Parking Division will take over meter maintenance and money collections, but not enforcement); and continuing to invest in technology and automation to parking to improve user friendliness, enhance revenue and reduce operating costs, which is already part of the 2009 budget process.  Other recommendations from Phase One, involve comprehensive long-range parking planning, consolidation of finances to fund improvements, and a reference to the City’s need to determine if it “wants to control its own destiny and develop parking to facilitate economic growth.”  In this regard, the report recommends land banking for at least a 250 space (net) future parking structure.

PHASE II

Following its receipt of Phase I of the parking study, the Steering Committee decided to move ahead with Phase II in order to ensure a comprehensive analysis that would provide assessment of possible sites and preliminary designs for potential new multi-story parking facilities downtown.  Desman Associate, as a result, moved ahead with the first segment of Phase II which included preliminary parking garage site elevations, estimated construction costs, and schematic garage designs based on a lot footprint.  The Committee requested that this work be done using a 500 net space facility because Desman’s analysis identified a long-term deficit of more than the 250 spaces, and if, in fact, the City was to pursue building a structure to meet the parking challenge, it should be adequate to meet downtown’s parking needs over the long, rather than short, term. 

For Phase II Desman Associates developed parking garage schematics for the parcels of land that currently make up lots 1, 3 and 4 accompanied by a technical memorandum detailing the particulars of each lot, to help the committee determine which scenario would best serve the current and future parking needs of the City.  Based on this analysis of existing lots, design requirements, cost effectiveness and location, the Steering committee determined that a 500+ net space garage at City Parking Lot #1 (Galleria site) was the best location for a new facility, should construction of a new facility be approved.  

Next the Committee approved moving forward with the final portion of the Desman Phase II analysis, which included a detailed financial review (cost estimates for construction, revenue projections, etc.) and a more specific preliminary design for a garage at parking Lot #1.    Please note that, in the interest of aesthetics, street appeal and the commercial vitality, the Steering Committee also requested that the garage facility include approximately 9,000 sq. ft. of retail space on grade fronting Delaware Avenue.  In addition, the committee requested that the garage concept be an automated one, utilizing the pay-on-foot technology currently used successfully in Lot #1. These requests were added to parking garage structure analysis. 

Desman estimated that the cost to build a parking garage on Lot #1 at $20,000 per space, and approximated that the retail space would cost $80 per sq. ft. to build.  When calculating the estimated overall costs, including operational expenses and income, Desman Associates anticipated that usage of the parking garage would remain consistent with the documented usage of current lot #1 – and further that the City would not increase parking rates at this facility, at least, not initially. Based on this conservative approach, Desman estimates of project development costs and the financing of same result in an annual deficit of $1,077,947 - $1,179,197, depending on the occupancy of the retail space, for a stand alone parking garage. 

When they reviewed this information, the Steering Committee discussed how such an investment in the parking infrastructure might be funded.  They asked the City Finance Director Dennis McFarland to assess the numbers provided by Desman, and determine how much of an increase in hourly parking fees, or other charges, would be necessary to make a parking garage on Lot #1 break even.  Finance Director Dennis McFarland reported that in order to have a positive net present value, the City would have to quadruple the current parking fees -- and -- double garage usage to result in a net present value of roughly $600,000 over a thirty year period. 

Faced with these figures, the Steering committee concluded that, at this present time, it is not financially feasible for the City to build a parking structure on its own.  They suggest expanding surface parking lots in the West District to address the immediate parking concerns, and beginning a long-range planning process, which might include a joint venture for a future-parking garage to address the imminent need

The conclusion of the “Parking Garage Needs Assessment Study” that the downtown area would benefit greatly from the addition of a parking garage and that the City should look for a partner for a potential joint venture to build one received a positive response from the business community.  The City is currently exploring opportunities and hopes to have more information as plans develop.  

Parking Meter Maintenance and Collections

Former Planning Intern Jonathan Rifkin completed his Master’s Degree at UD’s Institute of Public Administration this May, and as part of his academic requirements, presented an analytical paper on consolidating the on and off street parking administration in the City of Newark.  The analysis was originally requested of Planning Department staff by the Downtown Newark Partnership’s Parking Committee based on information they had collected about how other communities operate, and on complaints that they had received about non-functioning meters in downtown.   The meter issue was also discussed at a Council meeting in reference to meter and fine revenues.  In addition, Desman Associates (the Parking Garage Needs Assessment Garage Study Consultants) suggested early on in the process that consolidation of on and off street parking administration and revenues as a widely used tool to fund garage construction and maintenance.   

Based on the above, the Planning Department included research on the possibility of consolidating on and off street parking functions as part of this 2007’s Management Plan.  The research project was assigned to Jonathan as one of our more capable interns, who also happened to be in pursuit of a worthy AP topic to finish his UD course requirements.  Jonathan began his research in the summer 2006, and submitted his final report in May, 2007.  The report provided a thorough review of the matter, with extensive research and analysis of the pros and cons of consolidating on and off street parking administration in the City.  In a nutshell, the report indicated a very modest increase in revenues, but a marked increase in efficiency, through consolidating parking administration under one department.   The Parking Committee then reviewed the report and recommended that the City consider implementing its recommendations. 

As a result, on January 1, 2008 the responsibilities for on-street meter collections, deposits and maintenance were transferred to the Planning & Development Department’s Parking Division.  At the time, the maintenance of meters had been deferred and as many as 90 meters were not in service.  There were also inadequate maintenance supplies, and almost no monies budgeted for replacement parts.  The Division designed an efficient operational system for coin collection and deposits, and meter repair, working closely with the Parking Enforcement Officer to locate and immediately address broken or missing meters.  The Division assessed the revenue generated by meter location and concentrated on repairing and replacing the highest revenue generators first and has managed to repair countless meters so that the system is operating as optimally as possible.  Their efforts have made a considerable impact the City’s ability to generate fine revenues through meter enforcement.  In addition, on street parking revenues increased under the Parking Division’s direction:  Gross meter revenue increased by 27% in the first 2 quarters of 2008. 

The Committee is pleased to have been a part of this system-wide improvement. 

Parking Meter Change 

One of the things that came to the Committee’s attention through a UD Student focus group and from discussions with downtown customers, one of the things that people need while trying to patronize downtown businesses in change for parking meters.  The Committee considered locations for change machines and then decided that a more practical alternative was to ask downtown businesses if they would provide change for parking meters if asked by downtown patrons.  Several businesses responded positively and therefore, the Committee worked with ZZ House Design to come up with a window sticker which would identify the merchant as a friendly, downtown change-providing business, and also list the willing businesses on the DNP web page and provide the list to the University of Delaware for internal marketing.  The committee plans to expand this program by convincing more businesses to provide change in the upcoming year. 

 newark-change-sign

 

Free Parking Promotions  

Everybody loves free parking, and when there is a special event downtown, the Parking Committee is happy to oblige!  Working with other committees of the DNP, especially the Merchants’ and Events Committees, as well as the City Manager’s Office and the Newark Police Department in order to coordinate free parking for city events, as well as around the holidays - not to mention every Sunday throughout the year!  Free parking encourages out of town visitors to come enjoy Newark and helps downtown businesses draw in customers.  Over the 2007 holiday season alone, the city provided free parking over Thanksgiving weekend, Wednesdays in December, for Winterfest, as well as every day from mid- December to the end of the year so people could enjoy holiday shopping and festivities.  The free parking dates provide a sales boost for downtown businesses, and encourage people to shop in downtown Newark for the holiday season. 

Free parking promotions are planned for 2008 on Thanksgiving Weekend, Wonderful Winter Wednesdays and Winterfest from 3 PM on, and all day – every day from 6 PM on Friday, December 19 (the last day of UD exams) until Monday, January 4, 2009.  

Free parking was also provided for all Community Special Events held downtown throughout the year. 

Additional Parking Spaces

With Parking Committee guidance, the Downtown Parking Office was able to negotiate with the Christina School District for use of the parking lot behind the former district administration building located at 83 East Main Street.  This lot provides downtown with 64 parking spaces at a reasonable cost.  These spaces are leased to local residents and businesses on a monthly basis, as a source of revenue for parking improvements, as well as adding to the stock of off-street parking in a location convenient for residents and downtown employees.  When the Christina property recently sold to the University of Delaware, the Parking Division was quick to make arrangements to continue the parking lot lease until June 2009.  The Parking Committee and Division, again, deserve thanks and congratulations for a well-executed inventory expanding idea.   

Improvements to Existing Lots 

The Parking Committee is continually working on ways to improve the capacity and efficiency of our existing lots.  Additional directional signage has been installed at their suggestion to make it clear to customers how the lots operate and where to park.  The committee is also considering improvements to the validation programs and lot locational signage which will be considered next year.