Design Committee Accomplishments

Mission/Goals | Agenda | Members | Accomplishments | Projects

2008 Accomplishments

CSX Overpass Improvements: 

            The CSX railroad bridge, part of the DNP’s Mural-Gateway Project, is finally completed! The first phase of the bridge beautification project was completed in late 2005 and portrays a 114-foot long and 11½-foot high mural that transformed the graffiti-scarred railroad bridge into a dazzling and welcoming kaleidoscope of color.  The bridge mural has two sides and uses 35 bright colors to convey Newark’s vitality.  Whereas bright colors and large designs define the bridge mural, the abutments are intended to provide a “snapshot” of Newark today.  The two concrete abutment canvasses pay homage to large events that Newark hosts, such as “Community Day,” “Taste of Newark” and the “Halloween Parade and Trick or Treat Main Street.”  The abutment designs also give an aesthetic nod to the day-to-day activities that give Main Street its unique character and texture, such as shopping, eating and socializing.  Landscaping improvements were also installed, and are being maintained through agreement with the Porter Automotive Group.  The City of Newark Electric Department installed and energized new lights on the bridge to complete the project. 

The Downtown Newark Partnership would like to take this opportunity to thank mural designer and artist Terry Foreman, bridge preparation specialists Marinis Brothers, Inc., bridge painter and artist Chris Kanienberg, City crews and our generous donors without whom, this project would not have been possible.   

Delaware Avenue Mural Project 

            As the CSX Mural project neared completion, the Design Committee turned its attention to another anti-graffiti beautification project for downtown Newark, targeting the concrete abutments along the S-turn on Delaware Avenue, between Farmer Lane and Tyre Avenue.  DelDOT approval was required for this project since the abutment is actually a State facility.  After several renditions of potential mural designs and addressing DelDOT concerns that the mural be designed so as not to confuse motorists in believing that the concrete barrier was actually a “soft” barrier (landscaping, etc. rather than hard concrete), the State finally agreed to allow the DNP to install and maintain a mural in a stone-wall motif at the location.  The stone-wall look, which was also reviewed by the City of Newark’s Traffic Committee, actually highlights the fact that the S-turn barrier is a “hard” surface and vastly improves the aesthetics of the area which is within site of the new Transit Hub facility and the soon-to-be-constructed Pomeroy Walking and Biking Trail. In addition to mural conceptual approvals, the Committee spent a considerable amount of time raising monies to support the project.   The vast majority of those funds were raised through silent auctions, the sale of DNP and 250th Anniversary merchandise and the AZD/DNP 5 K Walk/Run.           

Artist Christian Kanienberg, owner of Wish Painting and Sculpture, designed the mural through its various renditions and painted the stone-wall motif mural during a two week in mid-August, 2008.  The result is a welcomed aesthetic and anti-graffiti improvement to a previously neglected area of downtown. 


Before:

 

Text Box: After:

 

 

 


After:

 

 

 

 

 

 

 

 

 

Design Guidelines 

            Downtown Newark’s Design Committee, as part of the City’s development review process, evaluates development proposals in the downtown area, on a voluntary basis, using the DNP’s Design Guidelines for Downtown Newark.  The Guidelines were originally adopted in 1997, and overhauled in 2007, and served as a guide for development in the downtown area.  The Committee meets with the developer and reviews the conceptual design for the potential project, and then reports to the results of their reviews to the City of Newark Planning Commission.   Since the last Annual Report, the committee has reviewed and commented on plans for 102 East Main Street, 137 East Main Street, 173-175 East Main Street, 209 East Main Street, 119 Elkton Road, and mostly recently 257 East Main Street.  The Planning Commission and City Council have both expressed gratitude to the committee for the Guidelines and their development reviews in the effort to keep downtown development in character with the rest of the town.  Developed in response to the construction of the large Galleria building and several other developments in the early to mid 1990s,  the Guidelines provide  guidance on types of architecture and design elements that fit best with Downtown Newark and the Committee’s goal of historic preservation and pedestrian scale infill construction.  

Comprehensive Streetscape Program - Phase 2 

            Phase One of the Comprehensive Streetscape Plan was completed in the Summer of 2006, including repaving of Main Street as well as some other improvements.  Phase Two encompassed pedestrian safety and aesthetic improvements, such as textured crosswalk placement, including bump outs and additional pedestrian scale lighting where possible and tree pit improvements.  The work is intended to improve the look and walk-ability of the town as well as the safety of the streets, including traffic calming effects of these additions.

            Phase Two of the Comprehensive Streetscape program was completed in the summer of 2008.  At the DNP’s urging to minimize the negative impact that road construction often has on existing businesses, the City took the stance that the construction must be kept to a specific timeframe and schedule – specifically traffic-disrupting construction was limited to between the hours of 10 PM and 10 AM each day, Sunday through Thursday, scheduled also so as not to interrupt any downtown special events, and be finally that it be completed before the students’ return for Fall semester.  Although the project started later than hoped, the contractor, Grassbusters Landscaping did a tremendous job of focusing on downtown’s need for expedited construction and worked ahead of schedule so that all traffic disrupting work was completed by the second week in August, 2008.  With minor concerns about tree pit design and damage to some trees during construction, which are currently being replaced, the City is pleased, overall, with the streetscape results.  The crosswalks on Main Street are far better delineated, and much more usable due to the pedestrian-scale lighting, and the bump-outs in particular.  The increased pedestrian traffic, and the increased visibility of pedestrian traffic, have traffic calming effects that serve to make Main Street safer and friendlier to visitors and residents alike. 

            The committee will now look to other streetscape improvements to complement first two phases such as benches and bike racks, improved signage, etc.           

Landscaping Tips 

As a way to beautify the downtown area in a relatively inexpensive manner, Design Committee Member and Certified Landscape Architect Lori Athey developed a document entitled Tips for Low Maintenance Plantings, which provides information about appropriate plant selection, surface preparation and easy maintenance.  Additionally, Ms. Athey offered free consultation for downtown businesses, an offer that was taken up by Dr. Singh’s 209 East Main Street building.  This type of service and attention to detail helps keep Downtown Newark looking great all year round!  

Architectural Assistance 

            The Design Committee works with businesses on Main Street to aid in exterior reconstruction and façade improvements.  The program provides a 1:1 matching grant of up to $2500 to property and business to make improvements to their buildings in the downtown area.  To begin the process, the business owner and the Design Committee work together to determine appropriate improvements for the building.  The Design Committee then works with the approved business to create conceptual drawings and obtain estimates; the construction can then proceed.  After the project is completed, the DNP awards a one-to-one matching grant up to $2500 to pay for the completed improvementsAlthough these funds were not utilized in this capacity this year, the Committee is pleased to offer the assistance and will continue to promote the opportunity to business and property owners. 

CSX Chapel Street Site

            On November 10, 2007, the Design Committee was able to conduct a clean up of the CSX overpass that crosses over Chapel Street.  Many volunteers, including members of the Design Committee, Mayor Funk and Councilman Stu Markham, and City crews worked diligently to remove trash, railroad debris, weeds and overgrowth from the site, and remove graffiti from the bridge and the abutment walls.  The City’s Parks and Recreation Department was then able to develop and implement a landscaping plan for the area, with the plantings being done in the late spring, 2008.   The landscaping is being maintained by Kevin Heitzenroder’s landscaping firm as a volunteer community service project.  The result is a much-improved gateway to downtown Newark.  

 

 

   

Due to concerns about lead-based paint on the structure, a bridge mural is not planned at this location.  However, the Committee is currently working with a student-run community service group of the University of Delaware called “Helping Hens” to create and install a mural on the cemetery wall immediately adjacent to the site.  The wall has often fallen victim to graffiti vandalism, and the Design Committee is hopeful that a mural at this location will further deter vandalism in the area.